Tuesday, 28 October 2008

To Do 2

My current 'to do' list at work:-
  1. Chase up parts for November's CD build
  2. Add beads to amplifier BOM
  3. Order beads for November's amplifier build
  4. Chase up boxes for remote control (REM004)
  5. Chase up IR emitter for REM003
  6. Print out parts list for front panels
  7. Print out parts list for chassises
  8. Chase designer for solid state relay specs
  9. Chase stores for any old amplifiers left to build
  10. Inventory of WIP in stores
  11. Chase up prototype job cards
  12. Make cable assemblies for next amplifier build
  13. Order red cable
  14. Order grinding discs
  15. Compile daily production report
  16. Calculate amplifier bom cost with new prices
  17. Update parts prices via Umi
  18. Update supplier part nos via Umi
  19. List amplifier test fails
  20. List CD plater test fails
  21. Put green LED on CD BOM
  22. Chase up supplier for surface mount versions of brown blob parts
  23. Kitting for next build of amplifier through hole parts
  24. Tidy production line area and label up bins for everything
  25. Check phono BOMs
  26. Return phono kit to stores
  27. Check reject / faulty / scrap metalwork
  28. Provide reject bins and post-it notes
  29. Get storeman to round up reject parts daily
  30. Go through box of unlabelled parts in storeroom
  31. Go through CD player parts box in storeroom
  32. Type up job cards
  33. Go over amplifier bom with designer
  34. Go over CD player bom with designer
  35. Kitting for last old CD player build
  36. Update purchasing list with UK alternative suppliers
  37. Username and password list for supplier websites
  38. Do query for alternative supplier required parts
  39. Rename all queries
  40. Batteries and remote on new product BOMs
  41. Change CAP006 to CAP087 on CD player front PCB BOM
  42. Make more jaunty videos in manufacturing
  43. Check BOMs for high-end preamp and power amp
  44. Check part built boards for preamp and power amp
  45. Kit for high-end power amp
  46. kit for high-end pre-amp
  47. Install server stuff on spare computer
  48. Put heatsink on amplifier BOM
  49. Finish entering K2CDP BOM
  50. Install Open Office on spare computer server
  51. Interpret "Components for K2 main PCB missing"
  52. Update the following BOMs urgently and send upwards
  53. new CD main PCB
  54. new CD front PCB
  55. new amp main PCB
  56. new CD product BOM
  57. new amp product BOM
  58. high-end product PCBs for components we populate
  59. Check parts shortages on remaining CD main PCBs
  60. Get new parts ordered
  61. Check parts shortages on remaining CD front PCBs
  62. Get new parts orderedImport flash test data to MRP system
  63. Kit mechanical parts for November builds
  64. Label and stock check front panel store
  65. Computer test amplifiers
  66. Quantities and locations BOM for new CD front PCB
  67. Chase up specs for IR receiver
  68. Find BOMs for mid-range products and send upwards
  69. Find BOMs for high-end products and send upwards

Well, I'm ready to ROCK today!!!

Added 9:32am 28-OCT-08
Get regulators for November ordered (2000 of each)
Chase next heatsink delivery
Make database documentation more complete

Added 14:08 28-OCT-08
Give designer excel spreadsheet of entire parts and supplier list
Return parts to stores
Move seeled kits away from storeroom
Find alt supplier for 11-way connector

Added 14:41 28-OCT-08
Order resistive loads
Construct resistive loads for soak testing K2INT