- Chase up parts for November's CD build
- Add beads to amplifier BOM
- Order beads for November's amplifier build
- Chase up boxes for remote control (REM004)
- Chase up IR emitter for REM003
- Print out parts list for front panels
- Print out parts list for chassises
- Chase designer for solid state relay specs
- Chase stores for any old amplifiers left to build
- Inventory of WIP in stores
- Chase up prototype job cards
- Make cable assemblies for next amplifier build
- Order red cable
- Order grinding discs
- Compile daily production report
- Calculate amplifier bom cost with new prices
- Update parts prices via Umi
- Update supplier part nos via Umi
- List amplifier test fails
- List CD plater test fails
- Put green LED on CD BOM
- Chase up supplier for surface mount versions of brown blob parts
- Kitting for next build of amplifier through hole parts
- Tidy production line area and label up bins for everything
- Check phono BOMs
- Return phono kit to stores
- Check reject / faulty / scrap metalwork
- Provide reject bins and post-it notes
- Get storeman to round up reject parts daily
- Go through box of unlabelled parts in storeroom
- Go through CD player parts box in storeroom
- Type up job cards
- Go over amplifier bom with designer
- Go over CD player bom with designer
- Kitting for last old CD player build
- Update purchasing list with UK alternative suppliers
- Username and password list for supplier websites
- Do query for alternative supplier required parts
- Rename all queries
- Batteries and remote on new product BOMs
- Change CAP006 to CAP087 on CD player front PCB BOM
- Make more jaunty videos in manufacturing
- Check BOMs for high-end preamp and power amp
- Check part built boards for preamp and power amp
- Kit for high-end power amp
- kit for high-end pre-amp
- Install server stuff on spare computer
- Put heatsink on amplifier BOM
- Finish entering K2CDP BOM
- Install Open Office on spare computer server
- Interpret "Components for K2 main PCB missing"
- Update the following BOMs urgently and send upwards
- new CD main PCB
- new CD front PCB
- new amp main PCB
- new CD product BOM
- new amp product BOM
- high-end product PCBs for components we populate
- Check parts shortages on remaining CD main PCBs
- Get new parts ordered
- Check parts shortages on remaining CD front PCBs
- Get new parts orderedImport flash test data to MRP system
- Kit mechanical parts for November builds
- Label and stock check front panel store
- Computer test amplifiers
- Quantities and locations BOM for new CD front PCB
- Chase up specs for IR receiver
- Find BOMs for mid-range products and send upwards
- Find BOMs for high-end products and send upwards
Well, I'm ready to ROCK today!!!
Added 9:32am 28-OCT-08
Get regulators for November ordered (2000 of each)
Chase next heatsink delivery
Make database documentation more complete
Added 14:08 28-OCT-08
Give designer excel spreadsheet of entire parts and supplier list
Return parts to stores
Move seeled kits away from storeroom
Find alt supplier for 11-way connector
Added 14:41 28-OCT-08
Order resistive loads
Construct resistive loads for soak testing K2INT